Farady oil immersed transformer Hanging Point Step

Before the oil immersed transformer hanging core work preparation:
⑴ tool material preparation: such as storage tank, oil filter, complete sets of wrenches, Dao Ben, oil-resistant rubber rope, white cloth, insulation cardboard.
⑵ equipment for the preparation of lifting: such as cranes, chain, lever hoist, tripod, wire rope, etc., if the chain, must be based on the height of the farady transformer and the weight of the hanger.
⑶ transformer oil treatment, take oil samples and test, do a good job in oil preparation, including oil filter paper.
⑷ do the preparation of oil pan, hand-core line.
The height of the hanger (h) shall not obstruct the lifting of the body.
So h = h1 + h2 + h3 + h4 + h5 test = h1 tank height h2 height of the device h3 rope height h4 pulley (or chain) minimum distance h5 standby height (300 ~ 500mm)
1. hanging beam
Pulley
3. Rope sets
4. body
5. Fuel tank
Dropping steps:
⑴ selected hanging core position, put the oil (placed under the broader market)
⑵ remove the explosion-proof tube, oil pillow, gas relay
⑶ remove the big cover bolts
⑷ use the balance iron will be hanging on the iron plate
⑸ check:
① core insulation
② core insulation
③ wear the core bolt insulation
④ tap switch contact insulation
⑤ high and low voltage lead
⑥ tank debris
⑦ heat pipe with or without clogging
⑧ telemetry insulation resistance
⑨ measure the DC resistance
⑹ all items after the inspection did not find the problem should be promptly loaded back, the iron back in the tank
⑺ strong cover bolts
⑻ install the removed accessories
⑼ into the qualified oil
⑽ static 6-10 hours after a full set of pressure test ⑾ site installation.